Hi,
I think...........the issue with using Settlement cost element (with category 22) in your config
Check F1 for the cost element category type.........below is the info..
- 22: External Settlement
- Used to
- settle
- order costs, project costs, or cost object costs to objects outside of CO. These objects could be assets (Asset Management), materials (Materials Management), or general ledger accounts (Financial Accounting). The R/3 System creates an accounting document when the costs are settled.
- Cost elements of this category cannot be used for settlement within CO (cost centers, orders, projects, and so on). Use secondary cost element category 21 for this purpose. The system does not create an accounting document when costs are settled within CO.
Hence COPA document is not getting created when you are settling the order...........try to change the cost element category to correct one......
br,rupesh